9/1/2022 - North Central Rail Trail: updated the map to add the new 1/2 mile branch to Spring Place. This was the RR that connected to Winchendon from Templeton.
11/15/2021 - Ware River Rail Trail: extended the map 4+ miles at the north end, to reach the railroad's original end in Winchendon.
11/30/2021 - Norton Rail Trail: updated the notes to indicate that the October 2021 Town Meeting voted to approve $700,000 for land easements in Norton and Mansfield.
11/11/2021 - Bike to the Sea Rail Trail: updated the map to show the 3000 feet that have been completed near the Encore Casino in Everett.
12/24/2019 - Wakefield-Lynnfield Rail Trail: updated Mossy Frog Studio's drone video to the new fall foliage version. Added old photo of the Lowell Street RR station.
12/14/2019 - Spencer Depot Rail Trail: added a photo of the South Spencer RR station and a copy of the 1878 annual report.
12/14/2019 - Marblehead Rail Trail: added the new 1/2 mile section in Salem that was opened September 2018.
12/7/2019 - Bruce Freeman Rail Trail: updated the map to show that the RT-2 bridge went out to bid. Winning bid will be announced in mid-January 2020.
11/27/2019 - Squannacook River Rail Trail: updated the map with the remaining 6 railroad station photos. Changed one section of the map to gold to mark the new stone dust construction that is scheduled to be completed in 2021.
10/20/2019 - Mass Central Rail Trail: updated map to indicate a new 1/2 mile completed section in Ware. Stone dust trail built by the EQLT (East Quabbin Land Trust
9/27/2019 - Bruce Freeman Rail Trail: updated the map to indicate phase-2C (West Concord) is now completed and open.
4/24/2019 - Bruce Freeman Rail Trail: updated the map to show that phase 2B, 2D are at the 100%, 25% design stages. Added a marker ( ) for the new Zagster Bike Share station in West Concord.
11/21/2018 - Columbia Greenway: Modified the map to show the gap in the trail north of Main Street and this year's restoration of the Great River Bridge.
11/18/2018 - Bruce Freeman Rail Trail: added the proposed extension north into Lowell, marked in red.
10/31/2018 - Ashburnham Rail Trail: added the 5 mile long future section up to the North Central Pathway in Winchendon.
5/9/2018 - Bruce Freeman Rail Trail: updated the map to set unique colors for each section of the project. Added the proposed Framingham section to the map.
4/14/2018 - Marblehead - Salem: merged the 2 old maps into one combined map.